Horizon Cloud on IBM SoftLayer - UK - Farnborough - Maintenance Window: Friday, July 02, 2021 01:00 UTC
Scheduled Maintenance Report for VMware Workspace ONE
Completed
The maintenance activity has been completed.

Thank you for your patience and apologies for any inconvenience caused.

Service reliability is a top priority at Horizon Cloud and we are making continuous improvements to better our systems.

Additional Information and Support:
Please visit Service Support Website at http://my.vmware.com or call Service Support Line at 1-877-4VMWARE if you need additional assistance.
Posted Jul 02, 2021 - 00:11 EDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 01, 2021 - 21:00 EDT
Scheduled
Please be advised that Horizon Cloud will be performing maintenance on management devices during this maintenance window.

Horizon Cloud Maintenance Window:
• Start: Friday, July 02, 2021 01:00 UTC
• End: Friday, July 02, 2021 04:00 UTC
• Datacenter Affected: UK - Farnborough

Impacted:
Virtual Desktops up-time and Network connectivity - We are expecting interruption in accessing existing desktops.
Provisioning of new Virtual Desktops - During this window provision of new Virtual Desktops will be impacted.
Virtual Desktops power operations - During this window power operations to existing Virtual Desktops will be impacted.
Changes to the existing pool – Any pool changes will be impacted.

Impact Duration:
A short (not more than 1 hour) customer impact is expected during this maintenance activity.

Service reliability is a top priority at Horizon Cloud, and we are making continuous improvements to better our systems.

Please visit Service Support Website at http://my.vmware.com or call Service Support Line at 1-877-4VMWARE if you need additional assistance.

Additional Information and Support:
VMware will provide additional updates on our Unified Status page (http://status.workspaceone.com) until this maintenance is completed.
Posted Jun 18, 2021 - 02:57 EDT