Horizon Cloud on IBM Cloud – Multiple Data Centers - Maintenance Window : Sunday August 29, 2021 00:00 UTC
Scheduled Maintenance Report for VMware Workspace ONE
Completed
The scheduled maintenance has been completed.
Posted Aug 30, 2021 - 09:17 EDT
Update
The maintenance activity has been completed.

Thank you for your patience and apologies for any inconvenience caused.

Service reliability is a top priority at Horizon Cloud and we are making continuous improvements to better our systems.

Additional Information and Support:
Please visit Service Support Website at http://my.vmware.com or call Service Support Line at 1-877-4VMWARE if you need additional assistance.

Thank You,
Communication Team
VMware Horizon on IBM Cloud
Posted Aug 28, 2021 - 22:10 EDT
Update
Scheduled maintenance is still in progress. We will provide updates as necessary.
Posted Aug 28, 2021 - 21:08 EDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 28, 2021 - 20:01 EDT
Update
Please be advised that Horizon Cloud partner IBM Cloud will be migrating VMware's private network into a VRF during the below rescheduled maintenance window. IBM will also be migrating the Direct Links in WDC02 over to a new set of routers.

Maintenance Window:
Start: Sunday, August 29, 2021 00:00 UTC
End: Sunday, August 29, 2021 08:00 UTC
Data center Affected: GERMANY - Frankfurt, JAPAN - Tokyo, UK - Chessington, UK - Farnborough, USA - Northern California, USA - Texas and USA – Virginia

Change Details:
· Reclaim all Direct Links on the VMware public Accounts (US/EMEA/APAC)
· Convert the private network into a VRF
· Migrate the WDC02 Direct Links over to the new routers
· Rebuild all Direct Links on the VMware public Account

Business Impact: Below listed objects may be inaccessible in 3 regions (US/EMEA/APAC)
· All Direct Links will be down for most of the maintenance
· VPN and Direct Link customers will be down during the VRF migration
· Virtual Desktops up-time and Network connectivity - We are expecting interruption in accessing existing desktops.
· Provisioning of new Virtual Desktops - During this window provision of new Virtual Desktops will be impacted.
· Virtual Desktops power operations - During this window power operations to existing Virtual Desktops will be impacted.
· Changes to the existing pool – Any pool changes will be impacted.

Impact Duration: 8 hours of customer impact is expected during this maintenance activity.

Apologies for any inconvenience caused.

Service reliability is a top priority at Horizon Cloud and we are making continuous improvements to better our systems.

Please visit Service Support Website at http://my.vmware.com or call Service Support Line at 1-877-4VMWARE if you need additional assistance.

Additional Information and Support: VMware will provide additional updates on our Unified Status page (http://status.workspaceone.com) until this maintenance is completed.

Thank You,
Communication Team
VMware Horizon on IBM Cloud
Posted Aug 17, 2021 - 00:35 EDT
Update
We will be undergoing scheduled maintenance during this time.
Posted Jul 26, 2021 - 00:54 EDT
Update
Please be advised that Horizon Cloud partner IBM Cloud will be migrating VMware's private network into a VRF during the below rescheduled maintenance window. IBM will also be migrating the Direct Links in WDC02 over to a new set of routers.

Maintenance Window:
Start: Saturday, August 28, 2021 13:00 UTC
End : Saturday, August 28, 2021 21:00 UTC
Data center Affected: GERMANY - Frankfurt, JAPAN - Tokyo, UK - Chessington, UK - Farnborough, USA - Northern California, USA - Texas and USA - Virginia

Change Details:
Reclaim all Direct Links on the VMware public Accounts (US/EMEA/APAC)
Convert the private network into a VRF
Migrate the WDC02 Direct Links over to the new routers
Rebuild all Direct Links on the VMware public Account

Business Impact: Below listed objects maybe inaccessible in 3 regions(US/EMEA/APAC)
All Direct Links will be down for most of the maintenance
VPN and Direct Link customers will be down during the VRF migration
Virtual Desktops up-time and Network connectivity - We are expecting interruption in accessing existing desktops.
Provisioning of new Virtual Desktops - During this window provision of new Virtual Desktops will be impacted.
Virtual Desktops power operations - During this window power operations to existing Virtual Desktops will be impacted.
Changes to the existing pool – Any pool changes will be impacted.

Impact Duration:
8 hours of customer impact is expected during this maintenance activity.

Service reliability is a top priority at Horizon Cloud and we are making continuous improvements to better our systems.

Please visit Service Support Website at http://my.vmware.com or call Service Support Line at 1-877-4VMWARE if you need additional assistance.

Additional Information and Support: VMware will provide additional updates on our Unified Status page (http://status.workspaceone.com) until this maintenance is completed.
Posted Jul 23, 2021 - 21:47 EDT
Scheduled
Please be advised that Horizon Cloud partner IBM Cloud will be migrating VMware's private network into a VRF during this maintenance window. IBM will also be migrating the Direct Links in WDC02 over to a new set of routers.

Maintenance Window:
Start: Saturday, July 31, 2021 13:00 UTC
End : Saturday, July 31, 2021 21:00 UTC
Data center Affected: GERMANY - Frankfurt, JAPAN - Tokyo, UK - Chessington, UK - Farnborough, USA - Northern California, USA - Texas and USA - Virginia

Change Details:
Reclaim all Direct Links on the VMware public Accounts (US/EMEA/APAC)
Convert the private network into a VRF
Migrate the WDC02 Direct Links over to the new routers
Rebuild all Direct Links on the VMware public Account

Business Impact: Below listed objects maybe inaccessible in 3 regions(US/EMEA/APAC)
All Direct Links will be down for most of the maintenance
VPN and Direct Link customers will be down during the VRF migration
Virtual Desktops up-time and Network connectivity - We are expecting interruption in accessing existing desktops.
Provisioning of new Virtual Desktops - During this window provision of new Virtual Desktops will be impacted.
Virtual Desktops power operations - During this window power operations to existing Virtual Desktops will be impacted.
Changes to the existing pool – Any pool changes will be impacted.

Impact Duration:
8 hours of customer impact is expected during this maintenance activity.

Service reliability is a top priority at Horizon Cloud and we are making continuous improvements to better our systems.

Please visit Service Support Website at http://my.vmware.com or call Service Support Line at 1-877-4VMWARE if you need additional assistance.

Additional Information and Support: VMware will provide additional updates on our Unified Status page (http://status.workspaceone.com) until this maintenance is completed.
Posted Jul 16, 2021 - 01:11 EDT